A project manager is leading the evaluation of three supplier bids. One of the bidding companies employs the project manager's sister as a senior manager, although she had no role in preparing the bid. What should the project manager do?
A
Continue the evaluation but score that bidder more strictly in order to stay neutral
B
Fully and proactively disclose the relationship to the sponsor and procurement, and refrain from deciding or influencing the selection until a mitigation plan is approved and the affected stakeholders consent
C
Resign from the project entirely and request reassignment to another initiative
D
Say nothing, because the sister had no involvement in preparing the bid